Estimated By
Your Phone
Your Email
EasyEst Estimating Software
By CSC Software
Any City, CA 99999
Page 1
05/14/2019
1:41 PM
Bid 25: Res. PB Sample for report
Bid Item Cost Only w/Markups by Sequence
Item
Code
Description
Unit
Quantity
Approx.
 Unit Cost
Total
Cost
Seq
*** Foundation ****
1
3.001300
15X18 Footing
250.00
LF
111.10
27,775.65
2
3.002500
Conc Slab 4''
1,500.00
SF
1.30
1,958.15
3
3.003000
Fill Dirt Below Slab Sub
15.00
CF
15.07
226.05
4
3.003500
Concrete Steps   Sub‑Bid
35.00
LF
38.70
1,354.50
5
3.004800
Sand & Wire      Sub‑Bid
2.00
SF
28.37
56.74
6
3.031100
# 3 (3)Per Run‑Rebar
150.00
LF
0.66
99.75
7
3.030100
6X6 10/10 Wire Mesh
5.00
SF
39.34
196.70
8
*** Insulation ***
9
7.023400
R‑19 Walls
2,500.00
SF
0.36
918.75
10
7.023700
R‑19 Ceil. Batts
1,500.00
SF
0.36
551.25
11
*** Finish ***
12
9.010700
1/2Drywall  8'H Intwall
175.00
LF
4.62
808.50
13
8.001700
Door‑Ext 3‑0X6‑8 Df 4Pan
1.00
EA
337.50
337.50
14
8.010500
Door 2‑6 Pre‑Fit H/C
3.00
HB
108.25
324.75
15
8.034300
Door‑Fold  6‑0X8‑0    Hb
2.00
EA
234.60
469.20
16
9.000300
Stucco Std.Fin. 9'High
250.00
LF
18.90
4,725.00
17
*** BID TOTAL  PRICE *** =
48,161.04
10.00%
3,980.25
Subtotal ‑
4,378.27
Overhead ‑
10.00%
Profit ‑
39,802.49
Your tag line or anything or nothing here